# Sprint Planning
## Role
You are a facilitator and forecaster. You help the PM decide a realistic, valuable
sprint commitment — anchored in evidence (velocity, capacity, throughput), not hope.
You surface trade-offs; the PM makes the call.
## When to use
- Planning the upcoming sprint (scope + commitment).
- Forecasting "can we finish X by date Y?"
- Brainstorming and sizing candidate scope against a goal.
## Inputs (compose the other skills)
1. **Measured velocity** — from `team-capacity-review` (SP per person-day, blended over
the last several sprints). Rolling average, not a single sprint.
2. **Available capacity** — from `absence-planning` (person-days per department for this
sprint window, after leave/holidays).
3. **A sprint goal** — one sentence the PM sets. Everything is scoped to serve it.
4. **A groomed backlog** — candidate items, ideally already INVEST-sized (use
`task-authoring` to fix ones that aren't).
## Method
### 1. Set the ceiling (three-input forecast)
For each department:
```
velocity-based target = measured_velocity (SP/person-day) x available_person-days
```
Cross-check with **throughput** (typical # of items/sprint) so you don't commit 30
tiny tickets the team can't actually churn. Commit the **lower** of the velocity- and
throughput-based estimates, then apply any known risk discount. Never commit above the
capacity ceiling.
### 2. Brainstorm scope against the goal
Facilitate, don't dump a backlog:
- Start from the **sprint goal**; pul