Produces a recurring project or programme status that survives a steering group: a RAG rating with stated criteria rather than sentiment, an explicit diff against the last report, decisions needed FROM the reader each with an owner and a date, and the rule that a status green for six consecutive weeks is not a status. Use when assembling a weekly or monthly update from systems of record, when a status is written but reads as reassurance, or when a project went from green to red with nothing in between. Trigger on 'write the status report', 'weekly project update', 'steerco update', 'what do I tell the steering group', 'RAG status', 'update on the programme'. Not for the post-hoc analysis of something that already failed (use engineering-incident-postmortem), not for communicating a roadmap to a broad audience (use product-roadmap-communication), and not for a board pack where decision rights and options analysis are the substance (use executive-board-pack-preparation).
alihusains/enterprise-skills · ★ 0 · AI & Automation · score 73
Install: claude install-skill alihusains/enterprise-skills
# Recurring project status reporting ## Purpose Status reports fail in one specific way: they report activity instead of position, and they rate confidence instead of measuring it. The result is a project that is green until the week it is not, because "green" meant "the team is working hard" rather than "the plan of record is still achievable". This skill fixes the RAG criteria, forces a diff against the previous report, and puts the decisions the reader must make — with dates — where they cannot be missed. ## Prerequisites - **Inputs:** the previous status report, the plan of record (baseline scope, dates, budget), and the current position from the systems of record — the tracker, the finance actuals, the risk log. A status written from memory or from a stand-up recollection reports mood. - **Access:** read access to those systems. If the tracker is stale, that is itself the finding — report the staleness with its as-of date rather than presenting old data as current. If there is no baseline to measure against, say so and stop rating: without a plan of record, RAG is opinion, and the first deliverable is agreeing the baseline. ## RAG criteria Rate against the plan of record, not against effort. Rate each dimension separately, then take the **worst** as the overall — averaging hides the thing that will hurt you. | Rating | Criterion | | --- | --- | | Green | Scope, date and budget are all forecast within the agreed baseline and tolerance, using current know