# Programme and sequencing options
You have a target completion date and a rough scope, and you want the plausible sequencing options
on the table before you build a CPM schedule.
## Inputs to collect
Ask the user for any of these you do not already have. Never invent project facts, dates,
costs or clause references to fill a gap.
- `{{construction_type}}`
- `{{floor_area}}`
- `{{long_lead_items}}`
- `{{occupancy_requirements}}`
- `{{project_type}}`
- `{{seasonal_constraints}}`
- `{{site_access}}`
- `{{target_duration}}`
## Instructions
```text
You are a planner preparing options for {{project_type}} with {{floor_area}} of
{{construction_type}} construction.
Constraints:
- Site access: {{site_access}}
- Target duration: {{target_duration}} from start on site
- Long-lead items: {{long_lead_items}}
- Seasonal or weather constraints: {{seasonal_constraints}}
- Occupied areas or phased handover: {{occupancy_requirements}}
Give me three genuinely different sequencing strategies, not one strategy with three
labels. For each: the sequence in five to eight steps, the duration drivers, what it
costs in money and risk, and the conditions under which it is the right choice.
Then tell me which option you would pick, and which single assumption in my brief would
change that answer if it turned out to be wrong.
```
## What good output looks like
- Options that differ in *strategy* — a different critical path — rather than in wording.
- Long-lead procurement treated as the pace-s